Scénario #19503
Étudier le portage de la synchronistation Scribe -> AD (Eole-AD) sur une version supportée d'EOLE
Status:
Terminé (Sprint)
Priority:
Normal
Assigned To:
-
Category:
-
Target version:
Start date:
03/27/2017
Due date:
04/14/2017
% Done:
100%
Estimated time:
(Total: 18.00 h)
Spent time:
(Total: 20.65 h)
Story points:
3.0
Remaining (hours):
0.00 hour
Velocity based estimate:
Description
Subtasks
Related issues
History
#1 Updated by Joël Cuissinat over 6 years ago
- Due date set to 03/24/2017
- Target version set to sprint 2017 10-12 Equipe MENSR
- Start date set to 03/06/2017
#2 Updated by Scrum Master over 6 years ago
- Target version changed from sprint 2017 10-12 Equipe MENSR to sprint 2017 13-15 Equipe MENSR
#3 Updated by Joël Cuissinat over 6 years ago
- Related to Scénario #20195: Finaliser le portage du projet Eole-AD en 2.5.2 et 2.6.2 added
#4 Updated by Joël Cuissinat over 6 years ago
- Status changed from Nouveau to Terminé (Sprint)