Étude migration Redmine

Added by Scrum Master over 5 years ago. Updated almost 5 years ago.

Status:
Terminé (Sprint)
Priority:
Normal
Assigned To:
Category:
-
Start date:
03/29/2016
Due date:
10/14/2016
% Done:

100%

Estimated time:
(Total: 11.00 h)
Spent time:
(Total: 16.00 h)
Story points:
5.0
Remaining (hours):
2.00 hours
Velocity based estimate:
Release:
Release relationship:
Auto

Subtasks

Tâche #15701: Tester la mise à jour redmine vers la dernière versionFerméDaniel Dehennin

Tâche #17402: Correctif sur le plugin redmine_git_hostingFerméDaniel Dehennin

Tâche #15700: Préparer une VM au niveau du redmine de prod EOLEReporté


Related issues

Copied to Distribution EOLE - Scénario #17501: Migration du Redmine du pôle EOLE Terminé (Sprint) 03/29/2016 11/25/2016

History

#1 Updated by Scrum Master over 5 years ago

  • Due date set to 04/15/2016
  • Target version set to sprint 2016 13-15 - Equipe MENESR
  • Start date set to 03/29/2016

#2 Updated by Scrum Master over 5 years ago

  • Assigned To set to force rouge

#3 Updated by Scrum Master over 5 years ago

  • Story points changed from 6.0 to 3.0

#4 Updated by Joël Cuissinat over 5 years ago

  • Due date deleted (04/15/2016)
  • Target version deleted (sprint 2016 13-15 - Equipe MENESR)
  • Start date deleted (03/29/2016)

#5 Updated by Daniel Dehennin about 5 years ago

  • Due date set to 07/08/2016
  • Target version set to sprint 2016 25-27 - Equipe PNE-SR
  • Start date set to 06/20/2016

#6 Updated by Daniel Dehennin about 5 years ago

  • Due date deleted (07/08/2016)
  • Target version deleted (sprint 2016 25-27 - Equipe PNE-SR)
  • Start date deleted (06/20/2016)

#7 Updated by Daniel Dehennin about 5 years ago

  • Due date set to 09/02/2016
  • Target version set to sprint 2016 28-35 - Équipe MENSR
  • Start date set to 07/11/2016

#8 Updated by Daniel Dehennin about 5 years ago

  • Due date deleted (09/02/2016)
  • Target version deleted (sprint 2016 28-35 - Équipe MENSR)
  • Start date deleted (03/29/2016)

#9 Updated by Daniel Dehennin about 5 years ago

  • Assigned To deleted (force rouge)

#10 Updated by Luc Bourdot about 5 years ago

  • Due date set to 10/21/2016
  • Target version set to sprint 2016 39-41 - Équipe MENSR
  • Start date set to 09/26/2016

#11 Updated by Joël Cuissinat about 5 years ago

  • Assigned To set to force rouge

#12 Updated by Scrum Master almost 5 years ago

  • Story points changed from 3.0 to 5.0

#13 Updated by Daniel Dehennin almost 5 years ago

  • Status changed from Nouveau to Terminé (Sprint)

Also available in: Atom PDF