Scénario #11045
Correction des problèmes d'affichage de formulaire OTP (EoleSSO 2.4.X)
Status:
Terminé (Sprint)
Priority:
Normal
Assigned To:
Category:
-
Target version:
Start date:
03/26/2015
Due date:
07/10/2015
% Done:
100%
Estimated time:
(Total: 2.00 h)
Spent time:
4.00 h (Total: 60.00 h)
Story points:
2.0
Remaining (hours):
0.00 hour
Velocity based estimate:
Release:
Release relationship:
Auto
Subtasks
Associated revisions
Mise en place d'entêtes HTTP sur l'ensemble des ressources
ref #11045 @2h
Encoding des templates OTP
ref #11045
Mise en place d'entêtes HTTP sur l'ensemble des ressources
ref #11045 @2h
Encoding des templates OTP
ref #11045
History
#1 Updated by Joël Cuissinat over 7 years ago
- Due date set to 05/29/2015
- Target version set to Sprint_2015_20-22 - Équipe MENESR
- Start date set to 05/11/2015
#2 Updated by Joël Cuissinat over 7 years ago
- Assigned To set to force verte
- Release set to Mise à jour 2.4.1.1
#3 Updated by Joël Cuissinat about 7 years ago
- Due date deleted (
05/29/2015) - Target version deleted (
Sprint_2015_20-22 - Équipe MENESR) - Start date deleted (
03/26/2015) - Release changed from Mise à jour 2.4.1.1 to EOLE 2.4.2
#4 Updated by Joël Cuissinat about 7 years ago
- Release changed from EOLE 2.4.2 to Mise à jour 2.4.1.2
#5 Updated by Scrum Master about 7 years ago
- Release changed from Mise à jour 2.4.1.2 to EOLE 2.4.2
#6 Updated by Joël Cuissinat about 7 years ago
- Assigned To deleted (
force verte)
#7 Updated by Scrum Master about 7 years ago
- Due date set to 07/10/2015
- Assigned To set to force bleue
- Target version set to Sprint_2015_26-28 - Équipe MENESR
- Start date set to 06/22/2015
#8 Updated by Scrum Master about 7 years ago
- Assigned To changed from force bleue to force jaune
#9 Updated by Joël Cuissinat about 7 years ago
- Status changed from Nouveau to Terminé (Sprint)