Scénario #11237
Évolution des remontées d'information de supervision des serveurs et alimentation infocentre
Status:
Terminé (Sprint)
Priority:
Normal
Assigned To:
-
Category:
-
Target version:
Start date:
04/20/2015
Due date:
05/07/2015
% Done:
100%
Estimated time:
(Total: 0.50 h)
Spent time:
(Total: 1.00 h)
Story points:
-
Remaining (hours):
0.00 hour
Velocity based estimate:
Subtasks
History
#1 Updated by Emmanuel IHRY almost 8 years ago
- Subject changed from Évolution des remontés d'information de supervision des serveurs et alimentation infocentre to Évolution des remontées d'information de supervision des serveurs et alimentation infocentre
#2 Updated by Emmanuel IHRY almost 8 years ago
- Status changed from Nouveau to Terminé (Sprint)