Scénario #11208
Intégrer dans la doc les modifications apportées par la version 2.4.2
Status:
Terminé (Sprint)
Priority:
Normal
Assigned To:
Category:
-
Target version:
Start date:
03/20/2015
Due date:
03/20/2015
% Done:
100%
Estimated time:
(Total: 48.00 h)
Spent time:
(Total: 29.77 h)
Story points:
2.0
Remaining (hours):
0.00 hour
Velocity based estimate:
Release:
Release relationship:
Auto
Subtasks
History
#1 Updated by Gérald Schwartzmann almost 6 years ago
- Release set to EOLE 2.4.2
#2 Updated by Joël Cuissinat almost 6 years ago
#3 Updated by Scrum Master almost 6 years ago
- Due date set to 07/10/2015
- Target version set to Sprint_2015_26-28 - Équipe MENESR
- Start date set to 06/22/2015
#4 Updated by Joël Cuissinat almost 6 years ago
- Assigned To set to force jaune
- Story points set to 8.0
#5 Updated by Scrum Master almost 6 years ago
- Story points changed from 8.0 to 2.0
#6 Updated by Joël Cuissinat over 5 years ago
- Status changed from Nouveau to Terminé (Sprint)