Scénario #11039
Évolutions "courier" nécessaires pour Envole
Status:
Terminé (Sprint)
Priority:
Normal
Assigned To:
Category:
-
Target version:
Start date:
03/26/2015
Due date:
06/19/2015
% Done:
100%
Estimated time:
(Total: 8.00 h)
Spent time:
(Total: 6.75 h)
Story points:
4.0
Remaining (hours):
0.00 hour
Velocity based estimate:
Release:
Release relationship:
Auto
Subtasks
History
#1 Updated by Scrum Master almost 6 years ago
- Due date set to 06/19/2015
- Target version set to Sprint_2015_23-25 - Équipe MENESR
- Start date set to 06/01/2015
#2 Updated by Scrum Master almost 6 years ago
- Assigned To set to force jaune
#3 Updated by Scrum Master almost 6 years ago
- Subject changed from Évolutions "courier" nécessaires pour Envole to Évolutions "courier" nécessaires pour Envole
- Story points set to 4.0
#4 Updated by Joël Cuissinat almost 6 years ago
- Status changed from Nouveau to Terminé (Sprint)